Microsoft Project Management a Glossary of Useful Terminology

The purpose of this article is to go through the mainWhat is a Critical Task
components and terms used in Microsoft Project andThe definition of a critical task is any task that with a
make them easier to understand. Project plannerschange of duration may positively or negatively affect
speak in a short hand that often excludes eventhe end date of the project if delayed
computer literate individuals.Tracking the Critical Path
Project software and project management is veryThe Gantt chart and network diagram two classic
jargon laden this article will attempt to simply keyviews in MS Project will display critical tasks and links in
project jargon for a new user. I for one have seen ared automatically to make these tasks easier to
dozen people sitting around a project plan discussingobserve and report.
whether the new WBS might help the varianceSlack Time
between the baseline plan and the project actual onlyTotal slack is the amount of time that lies off the
the project planner who was talking really knew whatcritical path. In other words changes to the duration of
was going on.these tasks may or may not affect the critical path.
What is a Project?Slack is the amount of time a task can be delayed
A project is any discrete set of interconnecting taskand still be on schedule. A 5 day task with a 10 day
with a defined start and end date. For example movingdeadline has 5 days of slack. A task with no slack is
an office from location A to B would have a definedautomatically critical. Imagine two tasks due to finish at
start date and a finish date culminating in a final launchthe same time. Packing computer equipment with one
party.day of duration and packing files with four days
What are Tasks?duration. If they both started at the same time the
A task is any piece of work requiring effort. Forpack equipment tasks would have three days of slack.
example moving offices might require 4 hours of workProject Calendar
effort.At its simplest this means remember to put in the bank
Durationsholidays. Otherwise at a meeting when someone
Work and duration is not always the same thing.notices a task that may be should have happened on
Monday to Friday I may have a five day task ina Monday slips to the
duration writing a report but my intention is too onlyTask Constraints
spend 50% of my time (work effort) on it.There are two main types of constraint in project
Milestonescalled soft constraints and hard constraints. An
Some tasks have no duration. Mile stone tasks haveexample of a cost constraint would be when moving
zero duration. Let's say that during a project moving anan office from A to B disconnect the computers as
office from A to B a decision needs to be madelate as possible so people can still send and receive
between two similar sites. This meeting to decide theemails. No specific date in mind. As an example of a
location would be described as a stage or milestone.hard constraint imagine that when the office has
Milestone tasks are displayed by default in MS Projectmoved the computers need setting up and you need
with a diamond shape.to book in a network engineer. This would be an
Linking Tasksexample of a hard constraint the work must be
Everyone understands the concept that one taskexecuted on that booked day.
finishes; let's say distributing boxes and the next oneSplitting Large Tasks
begins packing files. This is a linear of the world. TheSome times a task name might be too general to
reverse is also true one task cannot finish until anothermanage. You might have a task called Selecting the
has begun. For example the canary down the coalsite (duration 20 days). However, this could by split
mine cannot retire until the new air monitoring systemdown into smaller tasks known as subtasks i.e. within
is up and running. It is also possible that two tasks couldthe larger task Plan the move there might be smaller
start at the same time. In the new offices onetask to talk to a solicitor, draw up site layouts for
tradesman could be laying carpet tiles in the sameprospective sites, check transport links etc. When
room at the same time as a painter tackling the ceiling.linked din this way the major task is referred to as a
Similarly two tasks could have a finish to finishsummary bar.
relationship packing the furniture and computer mightProject Resources
have a finish to finish relationship with each other inThese are the people, rooms, equipment, Materials that
readiness for the next task of moving everything towill be used or consumed by the project. These
the new office. A final possibility might be that tworesources can be prioritized so that if for example a
tasks have no logical relationship with each other butsolicitor was over allocated work and expected to
just need to be independently completed before thecomplete to reports each taking ( 8 hours) on the.
project is completed.It would be possible to use different techniques to level
Format Time-scaleout their workloads
If a hospital was creating a template for the perfectResources also have calendars which can be used to
heart bypass operation they would be working in hoursenter their holidays and also any delays in their
and minutes but if London Underground were replacingschedule caused by sickness for example.
an escalator they would be working in day, weeks andLags leads and Delays
months.When moving an office from A to B half way through
Network Diagramthe task of distributing boxes presumably some one
It is possible to view your project plan in many wayshas a box therefore packing could begin. Or you could
one is a network diagram which is a flow diagram tosay 1 hour into the task distributing boxes the task of
show how the tasks relate to each otherpacking could begin.
Gantt chartAn alternative could be the new office is being painted
This few shows the task names on the left hand sideso a lap or gap of 2 days might be left for the paint to
of the screen and displays the tasks as bars on thedry before the new carpets are laid.
right hand side underneath a time scale. Gantt chartsA delay is different to a lag. Imagine the painter were
were initially named after a planner called Henrydue to start painting on the Monday but didn't arrive on
Laurence Gantt who worked as a mechanicalsite to scheduling error until Tuesday this would be an
engineer famous for his highly visual scheduling andunforeseen delay
monitoring diagram. Gantt Charts are drawn to displayResource Driven v Fixed Duration
planned and actual project progress. A commonlyIf it takes 1 day for a driver to get from London to
accepted project management instrument these days,Glasgow how long would it take two driver? Of
it was an innovation of world-wide significance incourse the answer is the same maybe longer if they
created while ship building during World War 1. Ganttchat. However, if two people are packing files instead
charts were subsequently used to monitor largeof one you would expect the task to be complete
construction projects like the Hoover Dam started inquickly, the first example is fixed duration and the other
1931 and Terminal 5 at Heathrow in London.is resource driven
Critical PathTracking & Baseline Plans
The shortest route through a series of interrelatedIf you imagine your project plan is a boat race
tasks. Should a task on the critical path slip then thebetween Oxford and Cambridge. Your Boat is Oxford
end date of the project would be jeopardized.(the schedule what you have told your colleagues will
Critical Pathhappen) tracking allows you to create a second boat
Most projects contain a large number of tasks. TheCambridge which is what actually happened. Every
critical path is the order of tasks that must be finishedtask in your schedule is a boat with an alter ego boat
for the project to be considered complete. This pathto track what actually happened. You can see which
dictates the final finish date of your project plan.tasks started and finished earlier or later than
The critical path is not primarily a list of vital tasks. It is aexpected. This is called tracking the variance between
specific sequence of tasks, each task depending onthe base line plan (the schedule you have set or
the last.announced and the actual outcome
As the project progresses, different sequences mightProject Costings
be named as critical. Consider a project with two vitalIt is also possible add cost information to both tasks
task sequences which we'll call selecting the newand resources. It could be that distributing boxes as a
office site and Moving in to new offices. At the onset,task has a fixed cost of £1000 but the
the first task is projected to take 9 months and theWBS
second is projected to take 6 months. Since the firstWork breakdown structure is just a notation eg 1.1, 1.2
task will take longer and is deemed as being on thea number sequence next to the tasks to make it
critical path.easier to understand
After three months work, should the first task performThese are just a few samples of the jargon
ahead of schedule with a new estimate of 5 additionalsurrounding Ms Project. Possibly you might want to
months more while the second has been delayed byconsider training to improve your productivity and join
three moths the latter task would now be on thegrowing MS Project community.
critical path?